Here we go, the most reliable informations from CIS. They build a 6 storeys building called Liberty House.
€10m Apartment Development
The construction of a new apartment building with 56no. residential units, a community facility and ancillary works. The site is bounded to the north by railway street, to the south by liberty park and in part by the steelworks apartments, to the west by block c liberty house and to the east by the kiln and the forge apartment buildings. the proposal provides for: the demolition of the existing 4-storey blocks e & f at liberty house, and for the construction of a hoarding/fencing around the area they currently occupy. Also proposed is the removal of most of the northern railings to liberty park and the removal of 9 mature trees in the northern section of the park following on from variation 50 to the 2005-2011 Dublin city development plan.
The construction of a landscaped pedestrian route linking liberty park to railway street. The construction of 16no. one bedroom residential units, 34no. 2 bedroom units, 6no. 3 bedroom units, a semi-basement car park for 27 cars and a community facility. the proposed building is generally 5 stories high with the south eastern corner at 6 stories high. ground floor duplex housing units are entered directly from the street or from the enclose landscaped courtyard, upper floor apartments are accessed via staircase/lift lobbies and some via shared access decks.
Project ID:
578226
Last Updated:
14/01/2013 15:19
Planning Reference:
3773/10
Planning Stage:
Detailed Plans Granted
Decision Date:
22/12/2011
Funding Type:
Public
Finish Date:
05/11/2014
Units:
56
Car Parking:
27
Address:
Liberty house, Railway street, Dublin 1, Co. Dublin
Planning Authority:
Dublin City Council
Contract Stage:
On Site
Application Date:
14/10/2010
Construction Type:
New Build
Start Date:
02/01/2013
Duration:
22 months
Storeys:
6
Value:
€10,000,000
Liberty House, Railway Street, Dublin 1 - a bit of history
Companies
Promoter
Name:
Dublin City Council
Contact:
Mr. Gerry Devlin
Address:
Housing Construction Branch, Block 1, Floor 6, Civic Offices, Dublin, Co. Dublin
Phone:
+353167961111
Email:
gerry.devlin@dublincity.ie
Architect
Name:
Paul Keogh Architects
Contact:
Mr. Paul Keogh
Address:
Cathedral Court, New Street, Dublin 8
Phone:
+35316791551
Fax:
+35316793476
Email:
info@pka.ie
WWW:
www.pka.ie
Agent
Name:
Dublin City Council
Address:
Block 4, Civic Offices, Wood Quay, Dublin, Co. Dublin
Phone:
+35316796111
Fax:
+35316777780
Email:
customerservices@dublincity.ie
WWW:
www.dublincity.ie
Main Contractor
Name:
Duggan Brothers (Contractors) Limited
Contact:
Mr. Gareth Anderson
Address:
9 Western Parkway Business Centre, Lower Ballymount, Dublin, Co. Dublin
Phone:
+35314500315
Fax:
+35314505024
Email:
info@dugganbrothers.ie
WWW:
www.dugganbrothers.ie
Nearly 100 drawings, floor plans, maps and other stuff to be found on this website :
http://www.dublincity.ie/AniteIMWebS...?grdResultsP=1
Latest news :
14/01/2013 Contract Stage updated to On Site 14/01/2013 Start Date updated to 02/01/2013 14/01/2013 We undestand sub-contractors will be domestic to the main contractor on this project. 02/01/2013 Description was updated 19/12/2012 Contract Stage updated to Main Contract Awarded 19/12/2012 Start Date updated to 14/01/2013 19/12/2012 Project Roles were updated 10/12/2012 Description was updated 27/11/2012 Start Date updated to 17/12/2012 27/11/2012 We understand a main contractor will be officially appointed in early December 2012. 13/11/2012 A main contractor is expected to be appointed imminently. 12/11/2012 Start Date updated from 05/11/2012 12/11/2012 Description was updated 12/10/2012 Description was updated 12/10/2012 Start Date updated to 05/11/2012 12/10/2012 Finish Date updated to 05/11/2014 12/10/2012 We understand a main contractor is expected to be officially appointed in the coming weeks. 30/05/2012 Exact construction schedule and plans have yet to be determined. 17/05/2012 Start Date updated from 07/05/2012 17/05/2012 Finish Date updated from 07/05/2014 18/01/2012 Contract Stage updated to Pre-Contract 18/01/2012 Start Date updated to 07/05/2012 18/01/2012 End Date updated to 07/05/2014 18/01/2012 Value updated to 10,000,000.00 18/01/2012 Tenders have been returned and are currently being assessed for the appointment of a main contractor. 18/01/2012 Description was updated 18/01/2012 Project Roles were updated 17/11/2011 Funding Type updated to Public 17/11/2011 Planning Stage updated to Detailed Plans Granted 17/11/2011 Contract Stage updated to Tender 17/11/2011 Decision Date updated to 22/12/2011 17/11/2011 Start Date updated to 14/02/2012 17/11/2011 Finish Date updated to 14/02/2014 17/11/2011 Project Roles were updated 17/11/2011 Construction work is expected to commence in Q1 2012. 17/11/2011 A main contractor is expected to be appointed in Q1 2012. 17/11/2011 Tenders are currently being sought for the appointment of a main contractor. 06/12/2010 Construction Type updated to New Build 27/10/2010 Number of storeys updated to 6 27/10/2010 Number of units updated to 56 27/10/2010 Number of parking spaces updated to 27 27/10/2010 Project Categories were updated 19/10/2010 Project Catgeories were updated 18/10/2010 Planning Stage updated to Detailed Plans Submitted 18/10/2010 Application lodged on 14/10/2010
http://www.dublincity.ie/swiftlg/apa...esults%3C/a%3E
This circled space it is the accurate place of the construction site of the new Libert House.
View of the site before the works commenced.
The end.
€10m Apartment Development
The construction of a new apartment building with 56no. residential units, a community facility and ancillary works. The site is bounded to the north by railway street, to the south by liberty park and in part by the steelworks apartments, to the west by block c liberty house and to the east by the kiln and the forge apartment buildings. the proposal provides for: the demolition of the existing 4-storey blocks e & f at liberty house, and for the construction of a hoarding/fencing around the area they currently occupy. Also proposed is the removal of most of the northern railings to liberty park and the removal of 9 mature trees in the northern section of the park following on from variation 50 to the 2005-2011 Dublin city development plan.
The construction of a landscaped pedestrian route linking liberty park to railway street. The construction of 16no. one bedroom residential units, 34no. 2 bedroom units, 6no. 3 bedroom units, a semi-basement car park for 27 cars and a community facility. the proposed building is generally 5 stories high with the south eastern corner at 6 stories high. ground floor duplex housing units are entered directly from the street or from the enclose landscaped courtyard, upper floor apartments are accessed via staircase/lift lobbies and some via shared access decks.
Project ID:
578226
Last Updated:
14/01/2013 15:19
Planning Reference:
3773/10
Planning Stage:
Detailed Plans Granted
Decision Date:
22/12/2011
Funding Type:
Public
Finish Date:
05/11/2014
Units:
56
Car Parking:
27
Address:
Liberty house, Railway street, Dublin 1, Co. Dublin
Planning Authority:
Dublin City Council
Contract Stage:
On Site
Application Date:
14/10/2010
Construction Type:
New Build
Start Date:
02/01/2013
Duration:
22 months
Storeys:
6
Value:
€10,000,000
Liberty House, Railway Street, Dublin 1 - a bit of history
Companies
Promoter
Name:
Dublin City Council
Contact:
Mr. Gerry Devlin
Address:
Housing Construction Branch, Block 1, Floor 6, Civic Offices, Dublin, Co. Dublin
Phone:
+353167961111
Email:
gerry.devlin@dublincity.ie
Architect
Name:
Paul Keogh Architects
Contact:
Mr. Paul Keogh
Address:
Cathedral Court, New Street, Dublin 8
Phone:
+35316791551
Fax:
+35316793476
Email:
info@pka.ie
WWW:
www.pka.ie
Agent
Name:
Dublin City Council
Address:
Block 4, Civic Offices, Wood Quay, Dublin, Co. Dublin
Phone:
+35316796111
Fax:
+35316777780
Email:
customerservices@dublincity.ie
WWW:
www.dublincity.ie
Main Contractor
Name:
Duggan Brothers (Contractors) Limited
Contact:
Mr. Gareth Anderson
Address:
9 Western Parkway Business Centre, Lower Ballymount, Dublin, Co. Dublin
Phone:
+35314500315
Fax:
+35314505024
Email:
info@dugganbrothers.ie
WWW:
www.dugganbrothers.ie
Nearly 100 drawings, floor plans, maps and other stuff to be found on this website :
http://www.dublincity.ie/AniteIMWebS...?grdResultsP=1
Latest news :
14/01/2013 Contract Stage updated to On Site 14/01/2013 Start Date updated to 02/01/2013 14/01/2013 We undestand sub-contractors will be domestic to the main contractor on this project. 02/01/2013 Description was updated 19/12/2012 Contract Stage updated to Main Contract Awarded 19/12/2012 Start Date updated to 14/01/2013 19/12/2012 Project Roles were updated 10/12/2012 Description was updated 27/11/2012 Start Date updated to 17/12/2012 27/11/2012 We understand a main contractor will be officially appointed in early December 2012. 13/11/2012 A main contractor is expected to be appointed imminently. 12/11/2012 Start Date updated from 05/11/2012 12/11/2012 Description was updated 12/10/2012 Description was updated 12/10/2012 Start Date updated to 05/11/2012 12/10/2012 Finish Date updated to 05/11/2014 12/10/2012 We understand a main contractor is expected to be officially appointed in the coming weeks. 30/05/2012 Exact construction schedule and plans have yet to be determined. 17/05/2012 Start Date updated from 07/05/2012 17/05/2012 Finish Date updated from 07/05/2014 18/01/2012 Contract Stage updated to Pre-Contract 18/01/2012 Start Date updated to 07/05/2012 18/01/2012 End Date updated to 07/05/2014 18/01/2012 Value updated to 10,000,000.00 18/01/2012 Tenders have been returned and are currently being assessed for the appointment of a main contractor. 18/01/2012 Description was updated 18/01/2012 Project Roles were updated 17/11/2011 Funding Type updated to Public 17/11/2011 Planning Stage updated to Detailed Plans Granted 17/11/2011 Contract Stage updated to Tender 17/11/2011 Decision Date updated to 22/12/2011 17/11/2011 Start Date updated to 14/02/2012 17/11/2011 Finish Date updated to 14/02/2014 17/11/2011 Project Roles were updated 17/11/2011 Construction work is expected to commence in Q1 2012. 17/11/2011 A main contractor is expected to be appointed in Q1 2012. 17/11/2011 Tenders are currently being sought for the appointment of a main contractor. 06/12/2010 Construction Type updated to New Build 27/10/2010 Number of storeys updated to 6 27/10/2010 Number of units updated to 56 27/10/2010 Number of parking spaces updated to 27 27/10/2010 Project Categories were updated 19/10/2010 Project Catgeories were updated 18/10/2010 Planning Stage updated to Detailed Plans Submitted 18/10/2010 Application lodged on 14/10/2010
http://www.dublincity.ie/swiftlg/apa...esults%3C/a%3E
This circled space it is the accurate place of the construction site of the new Libert House.
View of the site before the works commenced.
The end.